There are currently no known outstanding effects for the The Building (Approved Inspectors etc. ) Regulations 2010, PART 3A.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Textual Amendments
F1Regulations revoked (E.) (6.4.2024) by The Building (Registered Building Control Approvers etc.) (England) Regulations 2024 (S.I. 2024/110), regs. 1(3), 43(a)(i) (with regs. 44-47)
F2Pt. 3A inserted (6.4.2024) by The Building (Approved Inspectors etc.) (Amendment) (Wales) Regulations 2024 (S.I. 2024/244), regs. 1(1), 9
19B. For the purposes of section 53(7)(a)(iii) of the Act, section 52(1)(a) of the Act is prescribed.
19C. For the purposes of section 53B(5)(b) of the Act, a transfer certificate must contain the following information—
(a)statement describing the original work and the unfinished work;
(b)statement describing all the steps the approver has taken to determine, in accordance with section 53B(2) of the Act, whether the unfinished work contravenes any provision of the building regulations, in particular listing—
(i)each inspection or laying open of the work undertaken;
(ii)each report of any inspection or laying open of work produced;
(iii)any other assessment of the work which was considered;
(c)statement setting out the name and address of the registered building inspector from whom advice was obtained under section 54B(3) of the Act before giving the transfer certificate;
(d)declaration, signed and dated by the approver, confirming—
(i)the approver has inspected the unfinished work,
(ii)the approver has determined that, as at the date of the transfer certificate, the unfinished work does not contravene any provision of the building regulations,
(iii)each report or assessment referred to in the statement under paragraph (b) has been included in the transfer report given under section 53B of the Act,
(iv)the approver has obtained advice from a registered building inspector under section 54B(3) of the Act before giving the transfer certificate, and
(v)the approver has received the agreement of the person carrying out or intending to carry out the work to submit the transfer certificate and transfer report.
19D. For the purposes of section 53C(6)(a) of the Act, the prescribed period is 28 days.
19E. The grounds on which a local authority may reject a transfer certificate and transfer report are those prescribed in Schedule 3A.
19F.—(1) For the purposes of section 53D(5) of the Act, the following circumstances are prescribed—
(a)the business of the approver to which the initial notice relates has ceased for any reason, including in the case of insolvency;
(b)the person carrying out or intending to carry out the work has cancelled the initial notice under section 53D(3) of the Act because they were satisfied the approver was unable to carry out (or continue to carry out) their functions with respect to any of the work to which the initial notice relates;
(c)the approver is given a specified disciplinary order during the relevant period (as defined in section 53B(7) of the Act).
(2) In this regulation a “specified disciplinary order” means—
(a)any disciplinary order under section 58U(2)(b) of the Act (variation of registration) such that the approver is no longer able to carry out their functions with respect to any of the work to which the initial notice relates;
(b)any disciplinary order under section 58U(2)(c) of the Act (suspension of registration) excluding any suspension which is as a consequence of functions in relation to the unfinished work or work for the person carrying out the work;
(c)an order under section 58V of the Act (interim suspension for suspected serious contravention) excluding any interim suspension which is as a consequence of functions in relation to the unfinished work or work for the person carrying out the work;
(d)any disciplinary order under section 58U(2)(d) of the Act (cancellation of registration) excluding any cancellation which is as a consequence of functions in relation to the unfinished work or work for the person carrying out the work.]]
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: