F1PART 3Supervision of Work by F2Approvers
Word in Pt. 3 heading substituted (25.4.2024) by The Building Safety Act 2022 (Commencement No. 5 and Consequential Amendments) (Wales) Regulations 2024 (S.I. 2024/447), regs. 1(1), 3(a) (with reg. 6)
F3Approver's consultation with the fire and rescue authority12
1
This regulation applies where an initial notice is to be given or has been given in relation to the erection, extension or material alteration of a relevant building or in relation to building work in connection with a relevant change of use of a building and Part B of Schedule 1 to the Principal Regulations imposes requirements in relation to the work.
2
Where this regulation applies, the F3approver shall consult the fire and rescue authority—
a
before or as soon as practicable after giving an initial notice in relation to the work;
b
before or as soon as practicable after giving a relevant amendment notice in relation to the work;
c
before giving a plans certificate (whether or not combined with an initial notice); and
d
before giving a final certificate.
3
An F3approver who is required by paragraph (2) to consult the fire and rescue authority shall give to the fire and rescue authority—
a
in a case where the F3approver is consulting them in connection with an initial notice or an amendment notice, sufficient plans to show whether the work would, if carried out in accordance with those plans, comply with the applicable requirements of Part B of Schedule 1 to the Principal Regulations; and
4
An F3approver who is required by paragraph (2) to consult the fire and rescue authority—
a
shall have regard to any views they express; and
5
Where a local enactment would, if plans were deposited in accordance with building regulations, require the local authority to consult the fire and rescue authority before or during the carrying out of any work, the F3approver shall consult the fire and rescue authority in a manner similar to that required by the enactment.
6
In this regulation—
a
a “relevant building” is a building or any part of it to which the Regulatory Reform (Fire Safety) Order 2005 M1 applies, or will apply after the completion of building work;
b
a “relevant change of use” is a material change of use where, after the change of use takes place, the Regulatory Reform (Fire Safety) Order 2005 will apply, or continue to apply, to the building or any part of it;
c
a “relevant amendment notice” is an amendment notice where any of the work specified in the initial notice, as varied by the amendment notice, being work which could not have been carried out under the original notice (“additional work”), concerns the erection, extension or material alteration of a relevant building or is building work in connection with a relevant change of use of a building and Part B of Schedule 1 to the Principal Regulations imposes requirements in relation to the additional work.
Regulations revoked (E.) (6.4.2024) by The Building (Registered Building Control Approvers etc.) (England) Regulations 2024 (S.I. 2024/110), regs. 1(3), 43(a)(i) (with regs. 44-47)