- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made).
13.—(1) This regulation applies where an initial notice or amendment notice is to be given or has been given in respect of work in relation to which paragraph H4 of Schedule 1 to the Principal Regulations imposes requirements.
(2) Where this regulation applies, the approved inspector shall consult the sewerage undertaker—
(a)before or as soon as practicable after giving an initial notice in relation to the work;
(b)before or as soon as practicable after giving an amendment notice in relation to the work;
(c)before giving a plans certificate (whether or not combined with an initial notice); and
(d)before giving a final certificate.
(3) An approved inspector who is required by paragraph (2) to consult the sewerage undertaker shall give to the sewerage undertaker—
(a)in a case where the approved inspector is consulting them in connection with an initial notice or an amendment notice, sufficient plans to show whether the work would, if carried out in accordance with those plans, comply with the applicable requirements of paragraph H4 of Schedule 1 to the Principal Regulations; and
(b)in a case where the approved inspector is consulting them in connection with the giving of a plans certificate, a copy of the plans in relation to which the approved inspector intends to give the certificate.
(4) An approved inspector who is required by paragraph (2) to consult the sewerage undertaker—
(a)shall have regard to any views they express; and
(b)shall not give a plans certificate or a final certificate until 15 days have elapsed from the date on which the approved inspector consulted them, unless they have expressed their views to the approved inspector before the expiry of that period.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: