F1PART 3Supervision of Work by F3Approvers

Annotations:

F2Periods within which information on work to which an initial notice relates must be provided19A

1

For the purposes of section 53(4B) of the Act, the period within which a person shown in the initial notice as the approver (“P”) is required to give information to the local authority is 21 calendar days beginning with the date on which the local authority gives P a notice under section 53(4A). This period may be extended by mutual agreement between P and the local authority.

2

For the purposes of section 53(4C) of the Act, the period within which P is required to give information to the person carrying out or intending to carry out the work (“C”) is—

a

21 calendar days beginning with the date on which the local authority gave P a notice under section 53(4A), or

b

in relation to information requested by C pursuant to section 53(4C)(c), 21 calendar days beginning with the date on which C gives P a notice under section 53(4C)(c).