SCHEDULE 2Grounds for Rejecting an Initial Notice, an Amendment Notice, or a Plans Certificate Combined with an Initial Notice

Deficiencies in the proposed work

Drain connection

10.

In the case of the erection or extension of a building, the local authority consider that, in order to comply with the requirements of Part H of Schedule 1 to the Principal Regulations, a proposed drain or private sewer must discharge to an existing sewer, but the statement accompanying the notice does not describe such an arrangement.