[F1SCHEDULE 7E+WGrounds for Rejecting a Public Body's Final Certificate

Deficiencies in form and informationE+W

FormE+W

1.  The certificate is not in the prescribed form.

WorkE+W

2.  The certificate does not describe the work to which it relates.

Optional requirementsE+W

F12A.  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Absence of power to give certificateE+W

Capacity of public bodyE+W

3.  No public body's notice was in force with respect to the work described in the certificate at the time the certificate was given.

No proper signatureE+W

4.  A public body's notice was in force with respect to the work described in the certificate at the time when the certificate was given, but the certificate is not signed by or on behalf of the public body which gave that notice.

Lack of declarationE+W

Fire and rescue authorityE+W

5.  The public body was obliged by regulation 23 to consult the fire and rescue authority before giving the certificate, but the certificate does not contain a declaration that they were consulted in accordance with that regulation.

Sewerage undertakerE+W

6.  The public body was obliged by regulation 24 to consult the sewerage undertaker before giving the certificate, but the certificate does not contain a declaration that they have been consulted in accordance with that regulation.]