3.—(1) Prior to the closure of the storage site in accordance with paragraph 1(1) or (2) of this Schedule, the operator must submit a proposed post-closure plan to the authority for approval.
(2) That proposal must be based on the provisional post-closure plan, subject to any modifications proposed by the operator.
(3) In deciding whether to propose any such modifications, the operator must take into account—
(a)an analysis of the relevant risks;
(b)current best practice; and
(c)any improvements in the available technology.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: