SCHEDULE 1PROVISIONS TO BE INCLUDED IN A LICENCE
Grant of a storage permit1
If a storage permit is granted under a licence then, subject to regulation 12, paragraphs 2, 3 and 4 of this Schedule apply in respect of the storage site authorised under that storage permit.
Closure of storage site by the operator2
1
The operator must close the storage site where the conditions mentioned in regulation 8(1)(k) are met.
2
The operator may close the storage site if—
a
the consent of the authority has been given following an application under sub-paragraph (3), and
b
any conditions attached to that consent have been met.
3
An application for the authority's consent to the closure of the storage site must—
a
be made in writing and sent to the Department of Energy and Climate Change, and
b
contain the reasons why the operator proposes to close the storage site.
4
However, a storage site may not be closed under sub-paragraph (1) or (2) until the terms of the post-closure plan have been determined under regulation 13(3).
Post-closure plan3
1
Prior to the closure of the storage site in accordance with paragraph 1(1) or (2) of this Schedule, the operator must submit a proposed post-closure plan to the authority for approval.
2
That proposal must be based on the provisional post-closure plan, subject to any modifications proposed by the operator.
3
In deciding whether to propose any such modifications, the operator must take into account—
a
an analysis of the relevant risks;
b
current best practice; and
c
any improvements in the available technology.
Post-closure obligations4
1
After the storage site has been closed and until the licence is terminated, the operator must continue to—
a
monitor the storage site in accordance with paragraph 2 of Schedule 2,
b
comply with its reporting and notification obligations in accordance with paragraph 3 of Schedule 2 (with the exception of sub-paragraph (5)(b)), and
c
comply with its obligations to take corrective measures in accordance with paragraph 6 of Schedule 2.
2
However, for those purposes any reference to the monitoring plan or the corrective measures plan is to be read as a reference to the post-closure plan.
3
The operator must seal the storage site and remove the injection facilities in accordance with its obligations under Part 4 of the Petroleum Act 1998.
Extraction of stored CO25
The operator must not (and must not permit any other person to) extract stored CO2 from the storage site except with the prior written consent of the authority and in accordance with any conditions subject to which any such consent is given.
SCHEDULE 2PROVISIONS TO BE INCLUDED IN A STORAGE PERMIT
Acceptance and injection of CO21
1
In order to be injected into the storage site the CO2 stream must consist overwhelmingly of carbon dioxide, and must in particular satisfy the conditions in sub-paragraph (2).
2
The stream—
a
must contain no waste or other matter added for the purposes of disposal;
b
may contain incidental or trace substances (to the extent permitted by any legislation applicable to those substances), but only if the concentrations of all such substances are below the levels that would—
i
adversely affect the integrity of the storage site or the relevant transport infrastructure, or
ii
pose a significant risk to the environment or human health.
3
In sub-paragraph (2)—
a
“incidental substance” means a substance which has become associated with the CO2 either at its original source or as a result of the process of capture or injection; and
b
“trace substance” means a substance which has been added to the CO2 in order to assist in the monitoring and verifying of its migration after injection.
4
Before accepting and injecting the stream the operator must ensure that the conditions in sub-paragraphs (1) and (2) can be met, by carrying out—
a
an analysis of the composition of the stream, and in particular of any corrosive substances that may be present in it, and
b
an assessment of the risk that the stream will fail to comply with those conditions.
5
The operator must maintain a register, at a place and in a manner approved by the authority, of the quantities and properties of the CO2 streams that have been delivered to, and injected in, the storage site (including the composition of those streams).
Monitoring2
1
The operator must carry out a programme of monitoring of the storage complex and injection facilities, for the purposes specified in sub-paragraph (3).
2
Such monitoring must include (where possible) the monitoring of the CO2 plume, and (where appropriate) of the surrounding environment.
3
The purposes are—
a
the comparison of the actual and modelled behaviour of the CO2 (and the naturally-occurring formation water) in the storage site;
b
the detection of any significant irregularities;
c
the detection of any migration of CO2;
d
the detection of any leakage of CO2;
e
the detection of any significant adverse effects on the surrounding environment, and in particular on—
i
drinking water,
ii
human populations, and
iii
users of the surrounding biosphere;
f
the assessment of the effectiveness of any corrective measures taken;
g
updating the assessment of the safety and integrity, both short- and long-term, of the storage complex (including the assessment of whether the stored CO2 will be completely and permanently contained).
4
The monitoring must be based on the monitoring plan.
5
The monitoring plan must be updated in accordance with Annex II to the Directive, and in any event within five years of the approval of the original plan, in order to take account of—
a
changes to the assessed risk of leakage;
b
changes to the assessed risks to the environment and human health;
c
new scientific knowledge; and
d
improvements in best available technology.
6
The updated plan must be submitted for approval by the authority.
7
The authority may—
a
approve that plan, or
b
require the operator to make such modifications to it as the authority (after consulting the operator) considers necessary,
and the updated monitoring plan is the plan as so approved or modified.
8
Sub-paragraphs (5) to (7) apply to the further updating of an updated plan as they apply to the updating of the original plan.
Reporting, and notification of leakages and significant irregularities3
1
The operator must send to the authority a report in respect of each reporting period, containing the information specified in sub-paragraph (5).
2
The report must be sent to the authority no later than four weeks after the end of the relevant reporting period.
3
Unless the authority determines otherwise under sub-paragraph (4), the reporting periods are the period of one year beginning with the commencement of injection, and each subsequent yearly period.
4
At any time before the commencement of injection, or during a current reporting period, the authority may notify the operator that (beginning with the next reporting period) reporting periods are to be a period of less than one year that is specified in the notice.
5
The information is—
a
the results of the monitoring carried out under paragraph 2 of this Schedule (including details of the monitoring technology employed);
b
the quantities, properties and composition of the CO2 streams registered by the operator under paragraph 1(5) of this Schedule;
c
proof that the financial security required by paragraph 7 of this Schedule has come into effect and remains in force;
d
any other information requested by the authority that the authority considers relevant for the purposes of assessing compliance with the conditions of the storage permit or for increasing knowledge of the behaviour of the CO2 stored at the storage site.
6
If the operator becomes aware of any leakages or significant irregularities, the operator must immediately notify the authority.
7
If the operator becomes aware of any leakages, or of any significant irregularities which imply the risk of leakage, the operator must immediately notify the person who is the regulator in relation to the storage site for the purposes of legislation implementing the ETS Directive.
Notification and implementation of changes4
1
The operator must notify the authority of any change planned in the operation of the storage site, including any change concerning the operator.
2
A notification under sub-paragraph (1) must specify the target date.
3
Except where sub-paragraph (4) applies, such a notification must be made at least three months before the target date.
4
If the change solely concerns the operator, the notification must be made at least four weeks before the target date.
5
The change may not be implemented before the later of—
a
the target date, or any date notified under regulation 11(4)(b); and
b
the date notified by the authority in accordance with regulation 11(1)(b)(ii).
6
The change may not be implemented if the authority makes a notification to that effect under regulation 11(2)(b).
7
However, notwithstanding sub-paragraphs (5) and (6), the change may be implemented on or after the later of the dates mentioned in sub-paragraph (5)(a) if the authority has not before then made a notification under regulation 11(1)(b)(ii) or (2)(b).
Review, and modification or revocation of the permit5
The permit is to be reviewed, and where necessary modified or (as a last resort) revoked, by the authority in accordance with regulation 11.
Corrective measures6
1
If the operator becomes aware of any leakages or significant irregularities, the operator must take the necessary corrective measures and measures for the protection of human health.
2
The measures taken must include those set out in the corrective measures plan (but this is subject to regulation 10(3)).
Financial security7
1
The operator must maintain financial security that—
a
is of an amount (“the secured amount”) sufficient to ensure that the obligations specified in sub-paragraph (5) can be met,
b
is in force before the commencement of injection, and
c
remains in force until the licence is terminated.
2
However, if the storage permit is revoked the security must remain in force—
a
until a new storage permit is granted, or
b
if the storage site is closed following such revocation, until the licence is terminated.
3
Following each report made by the operator in accordance with paragraph 3(1) to (5) of this Schedule, the authority is to assess whether the secured amount is appropriate in the light of—
a
the assessed risk of leakage, and
b
the estimated costs of meeting the obligations specified in sub-paragraph (5).
4
If, following that assessment, the authority decides that the secured amount is to be adjusted—
a
the authority must notify the operator of the new amount that is required, and
b
where the secured amount is less than that new amount, the operator must ensure that it is increased to the new amount within three months of receiving that notification.
5
The obligations are—
a
all obligations of the operator arising under the storage permit, including those arising in respect of the closure of the storage site and during the period between such closure and the termination of the licence;
b
the obligation to pay the authority's costs under regulation 10(4)(b) or 12(6); F2...
c
any obligations of the operator arising in respect of the storage site under legislation implementing the ETS Directive; F3and
d
the obligation to provide the financial contribution to the authority in accordance with regulation 9(5) of the Storage of Carbon Dioxide (Termination of Licences) Regulations 2011.
6
Where the storage permit is revoked—
a
the obligations of the operator under this paragraph continue in effect until the licence is terminated, but
b
the assessment by the authority under sub-paragraph (3) is to be made at such intervals as the authority may determine.
F1SCHEDULE 3Powers of inspectors
1
The powers of an inspector are—
a
to enter, at any reasonable time (or, in an emergency, at any time) any premises, which the inspector has reason to believe it is necessary to enter;
b
on entering any premises by virtue of sub-paragraph (a), to—
i
be accompanied by any other inspector and, if the inspector has reasonable cause to apprehend any serious obstruction in the execution of the inspector’s duty, a constable; and
ii
take any equipment or materials that the inspector considers may be required for any purpose for which the power of entry is being exercised;
c
to make such examination and investigation as the inspector considers necessary, and for this purpose to install or maintain monitoring or other apparatus on the premises;
d
to direct that those premises or any part of them, or anything in or on them, shall be left undisturbed (whether generally or in particular respects) for so long as is reasonably necessary for the purposes of any examination or investigation under sub-paragraph (c);
e
to take such measurements and photographs and make such recordings as the inspector considers necessary for the purpose of any examination or investigation under sub-paragraph (c);
f
to take samples or cause samples to be taken of any thing found in or on the premises or in any air, water, land or seabed (including the subsoil of the seabed) in, on or in the vicinity of, the premises;
g
in the case of any thing found in or on the premises, cause it to be dismantled or subjected to any process or test (but not so as to damage or destroy it unless that is necessary);
h
in the case of any thing mentioned in sub-paragraph (g), take possession of it and detain it for so long as is necessary for all or any of the following purposes—
i
to examine it, or cause it to be examined and do to it anything which the inspector has power to do under that sub-paragraph;
ii
to ensure that it is not tampered with before the examination of it is completed; and
iii
to ensure that it is available for use as evidence in any proceedings for an offence under these Regulations or under Chapter 3 of the Energy Act 2008;
i
to require any person who the inspector has reasonable cause to believe is able to give any information relevant to any examination or investigation under sub-paragraph (c)—
i
to attend at a place and time specified by the inspector;
ii
to answer (in the absence of any person other than persons whom the inspector may allow to be present and a person nominated to be present by the person on whom the requirement is imposed) such questions as the inspector thinks fit to ask; and
iii
to sign a declaration of truth of that person’s answers;
j
to require the production of (or where the information is recorded in computerised form, the furnishing of extracts from), and inspect and take copies of or of any entry in—
i
any records which are required to be kept by virtue of any provision of any licence or storage permit;
ii
any records which the inspector considers it necessary to see for the purposes of any examination or investigation under sub-paragraph (c); and
k
to require any person to afford the inspector such facilities and assistance with respect to any matters or things within that person’s control or in relation to which that person has responsibilities as the inspector considers are necessary to enable the inspector to exercise any of the powers conferred by these Regulations and this Schedule.
2
Where an inspector proposes to exercise the power conferred by paragraph 1(g) in the case of a thing found on any premises, the inspector must, if so requested by a person who at the time is present on and has responsibilities in relation to those premises, cause anything which is to be done by virtue of that power to be done in the presence of that person.
3
Before exercising the power conferred by paragraph 1(g), an inspector must consult—
a
such persons having duties on the premises where the thing is to be dismantled or subjected to the process or test; and
b
such other persons,
as appear to the inspector appropriate for the purpose of ascertaining what dangers, if any, there may be in doing anything which the inspector proposes to do or cause to be done under the power.
Sch. 3 inserted (23.2.2012) by The Storage of Carbon Dioxide (Inspections etc.) Regulations 2012 (S.I. 2012/461), regs. 1, 6, Sch. 1