SCHEDULEInformation which is required to be notified to the Executive
1
Name and address of the owner or the lessor of the conventional tower crane installed at the construction site.
2
Address of the construction site at which the conventional tower crane was installed.
3
Particulars sufficient to identify the conventional tower crane including where known its date of manufacture.
4
Date of the thorough examination.
5
Name and address of the employer for whom the thorough examination was made.
6
Whether the thorough examination revealed any defects involving an existing or imminent risk of serious personal injury.