Search Legislation

The Harwich Parkeston Quay Harbour Revision Order 2010

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

23.—(1) This paragraph applies during the specified period if, in consequence of the construction of the specified works (including any dredging in connection with the construction, or to afford vessels access to those works), any accumulation of silt or other material, or any scouring or alteration of the tidal flow in the river is caused or created within the protected area.

(2) If the accumulation, scouring or alteration of tidal flow referred to in sub-paragraph (1) causes or creates a relevant concern, the protected interests may, within the specified period, request that the Company carry out such works or take such action to address that relevant concern.

(3) The Company, if so requested by the protected interests under sub-paragraph (2), shall carry out such works or take such action necessary to address that relevant concern, including without prejudice to the generality—

(a)repairing such damage;

(b)removing such accumulation of silt or other material; and

(c)restoring safe navigation and berthing,

within the protected area.

(4) If the Company fails to take the requested steps under sub-paragraph (3), the protected interests may themselves cause the work to be done and may recover from the Company the reasonable cost incurred by them in doing so.

(5) In this paragraph—

“the specified period” means the period—

(a)

during which the specified works on the foreshore or bed of the river are being constructed, ending five years after they have been completed; and

(b)

during which any temporary structures in connection with the specified works are being constructed, ending five years after they have been removed.

“a relevant concern” means—

(c)

damage to the harbour works of the protected interests;

(d)

an impediment to the free navigation of the protected area; or

(e)

prejudices safe navigation or berthing in that area.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources