Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
26.—(1) A rule-making authority may prepare standard rules for such regulated facilities as are described in those rules.
(2) In preparing or revising standard rules the authority must consult—
(a)such persons as it considers are representative of the interests of communities likely to be affected by, or persons operating, the regulated facilities described in the rules; and
(b)such other persons as it considers are likely to be affected by or have an interest in the rules.
(3) But the duty in paragraph (2) does not apply in relation to revisions which comprise only minor administrative changes.
(4) The authority must keep under review all standard rules published by it under this regulation and revise those rules when it considers necessary.
(5) The authority must publish on its website all standard rules prepared or revised by it under this regulation.
(6) The duty in paragraph (2) may be satisfied by a consultation carried out partially or wholly before the coming into force of these Regulations.
27.—(1) This regulation applies where a rule-making authority has published standard rules under regulation 26(5).
(2) At the request of the operator of a standard facility the regulator may include in the environmental permit authorising the operation of the facility a term providing that the relevant rules are conditions of the permit.
(3) If the regulator includes such a term, the relevant rules are conditions of the permit for the purposes of these Regulations, but there is no right of appeal under regulation 31 in relation to such a condition or the relevant rules.
(4) In this regulation, “relevant rules” means the standard rules which apply to the standard facility.
28.—(1) This regulation applies where the rule-making authority proposes to revise standard rules under regulation 26(4).
(2) Before the rule-making authority complies with regulation 26(5), the regulator must notify any operator who holds a relevant environmental permit—
(a)of the proposed revisions;
(b)of the date when the revised rules will be published, which must not be less than 3 months after the date the notification is served; and
(c)that on this date the revised rules will become conditions of the environmental permit.
(3) But the authority may publish the revised rules before 3 months after the date the notification is served if the revisions comprise only minor administrative changes.
(4) The revised rules take effect when published under regulation 26(5).
(5) In this regulation, “relevant environmental permit” means an environmental permit which will be affected by the proposed revisions.
29. The rule-making authority may revoke standard rules, but before doing so must consult the persons referred to in regulation 26(2).
30.—(1) This regulation applies to an environmental permit which includes a standard rules term if the standard rules applying by virtue of that term have been revoked by the regulator.
(2) The revoked rules continue to have effect until the regulator varies the permit under paragraph (3).
(3) As soon as reasonably practicable after the revocation of the rules, the regulator must vary the permit so as to—
(a)remove the standard rules term; and
(b)include such alternative conditions as it considers appropriate.
(4) In this regulation, “standard rules term” means a term of the type mentioned in regulation 27(2).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: