Approval and publication of a charging scheduleE+W

This section has no associated Explanatory Memorandum

25.  As soon as practicable after the charging authority approves a charging schedule in accordance with section 213 of PA 2008 it must—

(a)publish the charging schedule [F1, together with any report made under section 213(3B) of PA 2008,] on its website;

(b)make the charging schedule [F2, together with any report made under section 213(3B) of PA 2008,] available for inspection at the places at which the documents mentioned in regulation 16(1)(a) were made available;

[F3(c)give notice by local advertisement of the approval of the charging schedule, that a copy of the charging schedule is available for inspection, and of the places at which it can be inspected;]

(d)give notice to those persons who requested to be notified of the approval of the charging schedule that it has been so approved; and

(e)send a copy of the charging schedule to each of the relevant consenting authorities.