6 month period for deciding application to install facilities
This section has no associated Explanatory Memorandum
3.—(1) This regulation applies where—
(a)a person authorised to provide public electronic communications networks applies to a competent authority for the granting of rights to install facilities on, over or under public or private property for the purposes of such a network,
(b)a person authorised to provide electronic communications networks other than to the public applies to a competent authority for the granting of rights to install facilities on, over or under public property for the purposes of such a network, or
(c)a person applies to OFCOM for a direction applying the electronic communications code in the person’s case.
(2) Except in cases of expropriation, the competent authority must make its decision within 6 months of receiving the completed application.
(3) In this regulation “public electronic communications network”, “electronic communications network” and “OFCOM” have the same meanings as in Chapter 1 of Part 2 of the Communications Act 2003().