PART 2Subsystems
Project subsystems: F1UK verification assessment procedure17.
(1)
The F2UK verification assessment procedure for F3an approved body carrying out an assessment F4... is—
(a)
(b)
the applicable procedure set out in F6Schedule 4.
(2)
(a)
compile a technical file containing—
(i)
the items required by section 2.4 of F9Schedule 4, including the certificate of verification;
(ii)
documents relating to the conditions and limits of use of the project subsystem;
(iii)
documents relating to the characteristics of the project subsystem;
(iv)
manuals and instructions relating to the servicing, constant or routine monitoring, adjustment and maintenance of the project subsystem;
(v)
documentation or records of any decision of the Competent Authority under regulation 13(8) as to the extent to which any F10NTSN applies to the project subsystem; and
F11(vi)
documentation or records of a determination of the Competent Authority in relation to an exemption from an applicable NTSN, pursuant to regulations 14 and 14A; and;
(b)
assess the interface between the project subsystem and the rail system to the extent that such an assessment is possible based on the available information referred to in paragraph (3).