PART 3Activities to which article 4 applies and conditions

Cables and pipelines – authorised emergency inspection and repair34

1

Article 4 applies to a deposit, removal activity or dredging activity carried on for the purpose of executing emergency inspection or repair works to any cable or pipeline.

F12

Paragraph (1) is subject to the condition that—

a

the person carrying out the emergency inspection or repair works (as the case may be) notifies the licensing authority before the end of the period of 24 hours beginning with the time when the emergency inspection or repair works commence; and

b

the notification sets out the location, the circumstances giving rise to and the nature of the emergency works.

3

But article 4 does not apply to any such deposit falling within item 10 F2or to any such deposit made for the purpose of providing cable or pipeline protection.