61.—(1) After the granting of a UK marketing authorisation, the licensing authority may impose an obligation on the holder of the authorisation in accordance with either or both of —

(a)paragraph (4), in a case where paragraph (2) applies; or

(b)paragraph (5), in a case where paragraph (3) applies.

(2) This paragraph applies if there are concerns about the risks of a medicinal product that is the subject of a marketing authorisation.

(3) This paragraph applies if the understanding of the disease or the clinical methodology indicate that previous efficacy evaluations might have to be revised significantly.

(4) The obligation in this paragraph is to conduct a post-authorisation safety study.

(5) The obligation in this paragraph is to conduct a post-authorisation efficacy study.

(6) If concerns as described in paragraph (2) apply to more than one medicinal product, the licensing authority shall, following consultation with the Pharmacovigilance Risk Assessment Committee, encourage the marketing authorisation holders concerned to conduct a joint post-authorisation safety study.

(7) The obligation under paragraph (5) shall be based on the delegated acts adopted pursuant to Article 22b of the 2001 Directive while taking account of the scientific guidance referred to in Article 108a of the 2001 Directive.

(8) Where the licensing authority imposes an obligation under paragraph (4) or (5), it must without delay give written notice to the holder of —

(a)the imposition of the obligation;

(b)the justification for the imposition;

(c)the objectives and timeframe for submission and conduct of the study; and

(d)the opportunity to present written observations in accordance with paragraph (9) and the time limit specified for doing so.

(9) Where the holder so requests within the period of thirty days beginning on the day after the receipt by the holder of the notice referred to in paragraph (8), the licensing authority must provide the holder of the authorisation with an opportunity to present written observations in response to the imposition of the obligation within the time limit specified by the licensing authority in the notice.

(10) Where the holder presents written observations under paragraph (9), the licensing authority must withdraw or confirm the imposition of the obligation under paragraph (4) or (5) on the basis of the written observations as soon as is reasonably practicable.

(11) Paragraph (12) applies where the licensing authority—

(a)imposes an obligation under paragraph (4) or (5) and the holder does not present written representations under paragraph (9); or

(b)confirms the imposition of an obligation under paragraph (10).

(12) Where this paragraph applies, the licensing authority must vary the marketing authorisation to include the obligation as a condition of the marketing authorisation as if it were a condition imposed under regulation 59 (conditions of UK marketing authorisations: general).

(13) The licensing authority must notify the EMA that the marketing authorisation is subject to a condition included in accordance with paragraph (12).

(14) The holder of the authorisation must incorporate any condition included in a marketing authorisation in accordance with paragraph (12) into the risk management system for the product.

(15) Schedule 11, which makes provision about advice and representations in relation to proposals to vary or remove a condition to which a UK marketing authorisation is subject, shall apply in relation to the variation or removal of a condition included in a marketing authorisation in accordance with paragraph (12).

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules as a PDF

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources