PART 2PRINCIPAL POWERS
Development consent etc. granted by the Order5
1
Subject to the provisions of this Order and to the requirements in Part 2 (requirements) of Schedule 1 (authorised development and requirements) Network Rail is granted—
a
development consent for the authorised development; and
b
consent for the ancillary works,
to be carried out within the Order limits.
2
Subject to article 7 (limits of deviation) the authorised development comprising the works numbered in Part 1 of Schedule 1 may only be constructed in the lines and situations shown on the works plans and the levels shown on the sections.