[F1PART 8AE+W+SAnaerobic digestion installations and entitlement to generation payments

Textual Amendments

Ongoing obligation to provide annual declarations relating to feedstock typesE+W+S

38F.(1) The FIT generator or nominated recipient must submit to the Authority a declaration containing the following information for each annual reporting period—

(a)the total amount of electricity generated during the period by the relevant installation;

(b)details of feedstock used to make the biogas used to generate the electricity; and

(c)the proportion of the energy content of the biogas which was not derived from waste or residue, expressed as a decimal and rounded to 4 decimal places.

(2) The FIT generator or nominated recipient must provide the declaration within 3 months after the annual reporting period to which the declaration relates.

(3) The FIT generator or nominated recipient is not entitled to generation payments for electricity generated by the relevant installation during any period in which a declaration has not been submitted in accordance with this article.]