3.—(1) In regulation 5(3)(a) (meaning of “planning permission”) after paragraph (ii) insert—
“(iia)by a neighbourhood development order made under section 61E of TCPA 1990,”
(2) In regulation 9 (meaning of chargeable development) for paragraph (5) substitute—
“(5) In Wales, where the effect of a planning permission granted under section 73 of TCPA 1990(1) is only to change a condition subject to which a previous planning permission was granted by extending the time within which development must be commenced, the chargeable development is the development for which permission was granted by the previous permission as if that development was commenced.
(6) Where the effect of a planning permission granted under section 73 of TCPA 1990 is to change a condition subject to which a previous planning permission was granted so that the amount of CIL payable calculated under regulation 40 (as modified by paragraph (8)) would not change, the chargeable development is the development for which planning permission was granted by the previous permission as if that development was commenced.
(7) Where the effect of the planning permission granted under section 73 of TCPA 1990 is to change a condition subject to which a previous planning permission was granted so that the amount of CIL payable under regulation 40 (as modified by paragraph (8)) would change, the chargeable development is the most recently commenced or re-commenced chargeable development.
(8) For the purposes of paragraphs (6) and (7), the liability to CIL under regulation 40 should be calculated in relation to an application made under section 73 of TCPA 1990 as if the date on which the planning permission granted under that application first permits development was the same as that for the application for planning permission to which the application under section 73 of TCPA 1990 relates.
(9) For the purposes of paragraph (7), chargeable development is re-commenced where—
(a)the chargeable development (“the earlier development”) was commenced;
(b)work on the earlier development was halted and a different chargeable development (“the later development”) that was granted planning permission under section 73 of TCPA 1990 was commenced on the relevant land; and
(c)the later development was subsequently halted and the earlier development is continued.”
Section 73(5), inserted by section 51(3) of the Planning and Compulsory Purchase Act 2004 (c. 5), prevents such permissions from extending the time within which development must be commenced. This provision is yet to be commenced in relation to Wales.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: