The Greenhouse Gas Emissions Trading Scheme Regulations 2012

Requirement to notify the regulator if an emissions plan is not applied for [F1before 1st January 2015] U.K.

This section has no associated Explanatory Memorandum

33.—(1) [F2Subject to paragraph (4), without] prejudice to regulation 32(1), a person (“B”) who becomes a UK administered operator after 31st December 2012 must by the relevant date—

(a)apply to the regulator in accordance with regulation 32, or

(b)notify the regulator in accordance with paragraph (2).

(2) The notification must state that B does not expect to commence an aviation activity within the four-month period beginning with the relevant date.

(3) For the purposes of this regulation, “the relevant date” is the last day of the period of 12 weeks beginning with the date on which B became a UK administered operator.

[F3(4) This regulation does not apply after 31st December 2014.]