2012 No. 3104
Highways, England

The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012

Made
Coming into force
The Secretary of State for Transport having approved the Royal Borough of Kingston upon Thames Permit Scheme under section 34(2) of the Traffic Management Act 20041 makes this Order in exercise of the powers conferred by sections 34(4) and (5) and 39(2) of that Act.

Citation and commencement1.

This Order may be cited as the Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 and comes into force on 1st March 2013.

Interpretation2.

In this Order—

“the Royal Borough of Kingston upon Thames Permit Scheme” means the permit scheme set out in the Schedule in terms commonly known as the “London Permit Scheme” which was prepared and submitted to the Secretary of State by the Royal Borough of Kingston upon Thames and has been approved by the Secretary of State; and

“specified streets” has the meaning given by regulation 8 of the Traffic Management Permit Scheme (England) Regulations 20072.

Commencement of Permit Scheme3.

The Royal Borough of Kingston upon Thames Permit Scheme comes into effect on 1st March 2013.

Application of Part 8 of the Traffic Management Permit Scheme (England) Regulations 20074.

Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 shall apply to the specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

Signed by authority of the Secretary of State for Transport

Norman Baker
Parliamentary Under Secretary of State
Department for Transport

SCHEDULETHE ROYAL BOROUGH OF KINGSTON UPON THAMESPERMIT SCHEME

Article 2

EXPLANATORY NOTE
(This note is not part of the Order)

This Order gives effect to the Royal Borough of Kingston upon Thames Permit Scheme.

The Royal Borough of Kingston upon Thames Permit Scheme is designed to control the carrying out of works in specified streets in Kingston upon Thames by imposing an obligation to obtain a permit from the Royal Borough of Kingston upon Thames before undertaking the works.

Article 3 gives effect to the permit scheme, which will come into effect on 1st March 2013. The permit scheme referred to in this article is set out in the Schedule to the Order.

Article 4 applies Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 (which makes provision for the disapplication and modification of enactments in relation to specified works in specified streets) to the specified works and specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

A copy of the Royal Borough of Kingston upon Thames Permit Scheme is deposited and can be inspected at the offices of the Royal Borough of Kingston upon Thames, Main Reception, Guildhall 2, High Street, Kingston upon Thames, KT1 1EU and is available to inspect on the Borough’s website www.kingston.gov.uk.