Defence when energy performance certificate unobtainable

This section has no associated Explanatory Memorandum

37.—(1) A relevant person shall not be liable to a penalty charge notice for a breach of the duty imposed by regulation 6 where he can demonstrate that—

(a)he is not a person to whom the duty under regulation 7(2) previously applied and he made a request for an energy performance certificate as soon as possible after he became subject to the duty, and, despite all reasonable efforts and enquiries by the relevant person, he did not have in his possession or control a valid energy performance certificate at the relevant time; or

(b)in the case of a failure to make available an energy performance certificate to a prospective tenant—

(i)the prospective tenant was seeking to rent the building due to an emergency which required the tenant’s urgent relocation;

(ii)at the relevant time the relevant person did not have in his possession or control a valid energy performance certificate;

(iii)there was insufficient time in which the relevant person could reasonably have been expected to obtain a certificate before renting out the building to the prospective tenant; and

(iv)the relevant person has given a valid energy performance certificate to the tenant as soon as reasonably practicable after renting out the building.

(2) A relevant person shall not be liable to a penalty charge notice for a breach of the duty imposed by regulation 6 where he can demonstrate that—

(a)he is a person to whom the duty under regulation 7(2) applies;

(b)he complied with that duty; and

(c)despite all reasonable efforts and enquiries by the relevant person he did not have in his possession or control a valid energy performance certificate at the relevant time.

(3) In paragraph (1)(a) the reference to a request is to a request properly addressed to a person who usually provides or is likely to provide an energy performance certificate for the category of building in question and which includes such payment or an undertaking to make such payment as is usually necessary to obtain an energy performance certificate.

(4) In this regulation, “relevant time” means the point in time by which the relevant person is required to have made an energy performance certificate available to a prospective buyer or tenant by virtue of regulation 6(2).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources