The Galloper Wind Farm Order 2013

  1. Introductory Text

  2. 1.Citation and commencement

  3. 2.Interpretation

  4. 3.Development consent etc. granted by the Order

  5. 4.Maintenance of authorised project

  6. 5.Operation of an offshore electricity generating station and keeping of overhead lines

  7. 6.Requirements, appeals, etc.

  8. 7.Benefit of the Order

  9. 8.Public rights of navigation

  10. 9.Abatement of works abandoned or decayed

  11. 10.Deemed licence under the Marine and Coastal Access Act 2009

  12. 11.Saving for Trinity House

  13. 12.Crown rights

  14. 13.Street works

  15. 14.Agreements with street authorities

  16. 15.Authority to survey and investigate the land

  17. 16.Compulsory acquisition of land

  18. 17.Time limit for exercise of authority to acquire land compulsorily

  19. 18.Compulsory acquisition of rights

  20. 19.Private rights

  21. 20.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

  22. 21.Acquisition of subsoil only

  23. 22.Rights under or over streets

  24. 23.Temporary use of land for carrying out the authorised project

  25. 24.Temporary use of land for maintaining authorised project

  26. 25.For the protection of specified undertakers

  27. 26.Statutory undertakers

  28. 27.Recovery of costs of new connections

  29. 28.Application of landlord and tenant law

  30. 29.Operational land for purposes of the 1990 Act

  31. 30.Certification of plans etc.

  32. 31.Arbitration

  33. Signature

    1. SCHEDULE 1

      Authorised project

      1. PART 1 Authorised development

        1. 1.A nationally significant infrastructure project as defined in sections 14...

        2. 2.A nationally significant infrastructure project as defined in sections 14...

        3. 3.The grid coordinates for that part of the authorised development...

      2. PART 2 Ancillary works

      3. PART 3 Requirements

        1. 1.Interpretation

        2. 2.Time limits

        3. 3.Design parameters for wind turbines

        4. 4.Approval of detailed wind turbine design parameters by the Secretary of State

        5. 5.Further offshore design requirements

        6. 6.(1) The total number of offshore substation platforms, accommodation platforms...

        7. 7.(1) The number of cables forming part of the authorised...

        8. 8.(1) Each monopile foundation forming part of the authorised development...

        9. 9.Offshore safety management

        10. 10.Aids to navigation

        11. 11.The undertaker shall ensure that timely and efficient notices to...

        12. 12.The undertaker shall notify Trinity House, in writing, as soon...

        13. 13.The undertaker shall provide reports on the availability of aids...

        14. 14.The undertaker shall notify the UK Hydrographic Office, in writing,...

        15. 15.(1) The undertaker shall colour all structures yellow starting at...

        16. 16.(1) The undertaker shall exhibit such lights, with such shape,...

        17. 17.Provision against danger to navigation

        18. 18.Offshore decommissioning

        19. 19.Stages of authorised development onshore

        20. 20.Detailed design approval onshore

        21. 21.(1) The connection works and the transmission works shall be...

        22. 22.Provision of landscaping

        23. 23.Implementation and maintenance of landscaping

        24. 24.Fencing and other means of enclosure

        25. 25.Surface and foul water drainage

        26. 26.Archaeology

        27. 27.Ecological management plan

        28. 28.Construction code of practice

        29. 29.Construction hours

        30. 30.Control of noise during operational phase

        31. 31.Control of artificial light emissions

        32. 32.Detailed emergency response plan

        33. 33.European protected species

        34. 34.Restoration of land used temporarily for construction

        35. 35.Interference with telecommunications

        36. 36.Onshore decommissioning

        37. 37.Requirement for written approval

        38. 38.Amendments to approved details

    2. SCHEDULE 2

      Deemed licence under the Marine and Coastal Access Act 2009

      1. PART 1 Licensed marine activities

        1. 1.Interpretation

        2. 2.Details of licensed marine activities

        3. 3.This licence shall remain in force until the authorised scheme...

      2. PART 2 Conditions

        1. 1.Design parameters for wind turbines

        2. 2.Approval of detailed wind turbine design parameters by the Secretary of State

        3. 3.Further offshore design requirements

        4. 4.(1) The total number of offshore substation platforms, accommodation platforms...

        5. 5.(1) The number of cables forming part of the authorised...

        6. 6.(1) Each monopile foundation forming part of the authorised scheme...

        7. 7.Notifications and inspections

        8. 8.Chemicals, drilling and debris

        9. 9.Force majeure

        10. 10.Pre-construction plans and documentation

        11. 11.The undertaker shall ensure that a copy of any agreed...

        12. 12.(1) Except with the prior approval of the MMO, each...

        13. 13.Seasonal restrictions

        14. 14.Reporting of engaged agents, contractors and vessels

        15. 15.Equipment and operation of vessels engaged in licensed activities

        16. 16.Pre-construction monitoring

        17. 17.Construction monitoring

        18. 18.Post construction

        19. 19.Offshore decommissioning

        20. 20.Requirement for written approval

    3. SCHEDULE 3

      Streets subject to street works

    4. SCHEDULE 4

      Land in which only new rights etc., may be acquired

    5. SCHEDULE 5

      Land of which temporary possession may be taken

    6. SCHEDULE 6

      1. PART 1 For the protection of specified undertakers

        1. 1.For the protection of the utility undertakers referred to in...

        2. 2.In this Schedule— “alternative apparatus” means alternative apparatus adequate to...

        3. 3.This Schedule does not apply to apparatus in respect of...

        4. 4.Regardless of any provision in this Order or anything shown...

        5. 5.(1) If, in the exercise of the powers conferred by...

        6. 6.(1) Where, in accordance with the provisions of this Schedule,...

        7. 7.(1) Not less than 28 days before starting the execution...

        8. 8.(1) If in consequence of the exercise of the powers...

        9. 9.(1) Subject to sub-paragraphs (2) and (3), if by reason...

      2. PART 2 For the protection of EDF Energy

        1. 1.The following provisions of Part 2 of this Schedule shall...

        2. 2.Sizewell C proposed intake infrastructure

        3. 3.Quality of Sizewell B cooling water intake

        4. 4.Buffer zone for Sizewell B offshore infrastructure

  34. Explanatory Note