This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
20.—(1) Except where the connection works or the transmission works, as the case may be, are carried out in accordance with the plans (or relevant parts of the plans) listed in Requirement 21, no part of the relevant works shall commence until details of the layout, scale, levels and external appearance of the same, so far as they do not accord with the authorised plans, have been submitted to and approved by the relevant planning authority. The relevant works must be carried out in accordance with the approved details, unless agreed otherwise by the relevant planning authority.
(2) Any works approved by the relevant planning authority under sub-paragraph (1) shall accord with the principles of the design and access statement submitted with the application for this Order and be within the Order limits.
(3) No building forming part of Work Nos. 6, 8A, 8B or 10, shall exceed the relevant height limit for its proposed location specified on the height restriction plan above the approved floor level for that location.
(4) The floor level of Work Nos. 6 and 10 shall not be higher than 9 metres AOD.
(5) Work No. 6 shall not be brought into commercial operation (excluding commissioning) until Work No. 7 has been constructed.
(6) The height of the relocated communications mast shall not exceed 15 metres AOD, and its supporting pole shall not exceed 16 metres AOD.
(7) The width of the corridor occupied by the grid connection comprising Work Nos. 3B and 5, and any related associated development, once constructed, shall not exceed 23 metres, save for any part of the works where drilling is proposed, which part(s) shall not exceed 33 metres.
(8) No works shall be carried out in relation to the laying of cables or other works under Sizewell Gap until the detail of those works and their proposed methodology has been approved by the relevant planning authority, after consultation with the highway authority and EDF Energy (which shall not unreasonably delay its response to that consultation). The relevant works shall be carried out in accordance with the approved details, unless agreed otherwise by the relevant planning authority, after consultation with the highway authority and EDF Energy (which shall not unreasonably delay its response to that consultation).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: