Archaeology

26.—(1) Neither the connection works nor the transmission works (including in each case site clearance and preliminary earthworks) shall commence until in relation to the relevant works a written scheme of archaeological investigation has been submitted to and approved by the relevant planning authority, in consultation with Suffolk County Council.

(2) The scheme shall include an assessment of significance and research questions and—

(a)the programme and methodology of site investigation and recording;

(b)the programme for post investigation assessment;

(c)provision to be made for analysis of the site investigation and recording;

(d)provision to be made for publication and dissemination of the analysis and records of the site investigation;

(e)nomination of a competent person or organisation to undertake the works set out within the written scheme of investigation.

(3) Neither the connection works nor the transmission works shall commence until in relation to the relevant works the relevant site investigation has been completed in accordance with the programme and methodology included in the approved scheme, and such completion has been approved by the relevant planning authority.

(4) Neither the connection works nor the transmission works shall be brought into commercial operation (excluding commissioning) until in relation to the relevant works the site investigation and post investigation assessment have been completed in accordance with the programme in the approved scheme and the provision made for analysis, publication and dissemination of results and archive deposition has been secured.

(5) The written scheme in relation to the relevant works shall be carried out as approved, unless otherwise agreed with the relevant planning authority.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources