29.—(1) Construction work for the connection works and the transmission works and any construction-related traffic movements to or from the site of the relevant works shall not take place other than between 0700 hours and 1900 hours Monday to Saturday, with no activity on Sundays or bank holidays, save—
(a)where continuous periods of operation are required, such as concrete pouring and drilling;
(b)for the delivery of abnormal loads to the relevant works, which may cause congestion on the local road network;
(c)where works are being carried out on the foreshore;
(d)where connection works to the overhead power lines are being carried out;
(e)as otherwise agreed in writing with the relevant planning authority.
(2) All construction operations which are to be undertaken outside the hours specified in sub-paragraph (1) shall be agreed with the relevant planning authority in advance, and shall be carried out within the agreed times, unless otherwise agreed with the relevant planning authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: