Approval of detailed wind turbine design parameters by the Secretary of State

4.—(1) The authorised development shall not commence until the Secretary of State has received the Approval Application and issued the Approval Notice.

(2) An Approval Application shall include—

(a)the proposed Maximum WTG Number;

(b)the proposed WTG Specification;

(c)the proposed Minimum Clearance Level; and

(d)an explanation of how the proposed Maximum WTG Number, the proposed WTG Specification and the proposed Minimum Clearance Level, in combination, achieve the Percentage Reduction.

(3) The Approval Notice shall specify—

(a)the Maximum WTG Number;

(b)the WTG Specification, which shall comply with the requirements of paragraphs (a) to (c) of Requirement 3(1); and

(c)the Minimum Clearance Level, which shall comply with the requirements of paragraph (e) of Requirement 3(1).

(4) The Secretary of State shall not issue the Approval Notice unless he is satisfied, following consultation with Natural England, that the Maximum WTG Number, the WTG Specification and the Minimum Clearance Level, in combination, achieve the Percentage Reduction.

(5) The Approval Notice shall include a statement of—

(a)the reasons why the Secretary of State is satisfied that the Percentage Reduction is achieved; and

(b)where the Maximum WTG Number, the WTG Specification, or the Minimum Clearance Level is different from that proposed in the Approval Application, the reasons for the difference.

(6) The number of wind turbine generators forming part of the authorised development shall not exceed the Maximum WTG Number specified in the Approval Notice.

(7) Each wind turbine generator forming part of the authorised development shall conform to the WTG Specification specified in the Approval Notice.

(8) For each wind turbine generator constructed as part of the authorised development, the minimum distance between the lowest point of its rotating blade and the MHWS shall be at least equal to the Minimum Clearance Level.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources