The Galloper Wind Farm Order 2013

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Offshore safety management

9.—(1) No authorised development seaward of MHWS shall commence until the Secretary of State, in consultation with the MCA, has confirmed in writing that the undertaker has taken into account and adequately addressed all MCA recommendations contained within MGN371, “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues” and its annexes including full details of the Emergency Co-operation Plans (ERCoP) for the construction, operation and decommissioning phases as appropriate to the authorised development.

(2) The undertaker shall prepare and implement a project specific Active Safety Management System, taking account of safety and mitigation measures as identified within the Navigation Risk Assessment.

(3) The undertaker shall at its cost, provide and deliver to the MCA Hydrographic data (to IHO order 1a standard) of the extended SUNK East Traffic Separation Scheme.

(4) The undertaker shall at its cost, as soon as technically feasible following the commencement of construction works seaward of MHWS, remotely gather and provide to the MCA: Radar, AIS and VHF radio telephony information in relation to the extended SUNK East Traffic Separation Scheme to assist in managing shipping movements as a result of the authorised development. The information must be—

(a)gathered to adequately extend the marine traffic monitoring (VTS) range to effectively cover the Eastern extremity of the SUNK East Traffic Separation Scheme extension unless otherwise agreed by the MCA;

(b)delivered, in a format and within a timescale agreed by the MCA, so that it may be incorporated into the MCA’s systems for seamless display at CNIS; and

(c)provided by the undertaker to the MCA until the authorised development has been fully decommissioned in accordance with an approved programme under the 2004 Act.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources