The Galloper Wind Farm Order 2013

Pre-construction plans and documentation

12.—(1) Except with the prior approval of the MMO, each programme, statement, plan, protocol or scheme required to be approved under condition 10, must be submitted for approval at least four months prior to the intended start of construction, or survey. Any variation to the approved surveys under condition 10(2)(a)(iii) shall only be made following consultation with Natural England and JNCC.

(2) Any proposed variation to condition 10(2)(g)(iv) which would exceed the stated dimensions in that condition, shall only be agreed by the MMO after consultation with EDF Energy.