Regulations 4 and 6
SCHEDULE 1E+WInformation to be given in English registers of large raised reservoirs
1. Name and situation of reservoir.E+W
Commencement Information
I1Sch. 1 para. 1 in force at 30.7.2013, see reg. 1(b)
2. National grid reference of reservoir.E+W
Commencement Information
I2Sch. 1 para. 2 in force at 30.7.2013, see reg. 1(b)
3. Name and address of undertakers.E+W
Commencement Information
I3Sch. 1 para. 3 in force at 30.7.2013, see reg. 1(b)
4. A summary of the contents of all certificates or reports made under the 1975 Act, or the 1930 Act, including—E+W
(i)the name and address of the engineer giving the certificate or making the report;
(ii)the section of whichever Act the certificate is given under or the report is made;
(iii)where no final certificate has been given under the 1975 Act, a statement of that fact;
(iv)where no final certificate was given under the 1930 Act because the construction or alteration of the reservoir was completed before the commencement of that Act, a statement of that fact.
Commencement Information
I4Sch. 1 para. 4 in force at 30.7.2013, see reg. 1(b)
5. The following information if it is revealed by any certificate, report or statement—E+W
(i)the category of the reservoir (whether impounding or non-impounding);
(ii)year(s) in which the dam(s), reservoir walls or embankments(s) were completed;
(iii)the construction of the dam(s), reservoir walls or embankments(s) (i.e. whether constructed of earth, rockfill, gravity, buttress or by other means);
(iv)the level of the top of the dam(s), reservoir walls or embankments(s) of the reservoir with reference to Ordnance Datum;
(v)the top water level of the reservoir with reference to Ordnance Datum;
(vi)the maximum height of the dam(s), reservoir walls or embankments(s) measured in metres from the lowest natural level of the surrounding land, to the top of the dam(s), reservoir walls or embankments, excluding the height of the wave wall;
(vii)the capacity of the reservoir;
(viii)the water surface area of the reservoir at top water level (in square metres or square kilometres).
Commencement Information
I5Sch. 1 para. 5 in force at 30.7.2013, see reg. 1(b)
6. Name and business address of the supervising engineer or, if the reservoir is under the supervision of the construction engineer, of that engineer.E+W
Commencement Information
I6Sch. 1 para. 6 in force at 30.7.2013, see reg. 1(b)
7. Date when the next inspection is due under the 1975 Act or any date recommended for the next inspection under the 1975 Act by the supervising or inspecting engineer.E+W
Commencement Information
I7Sch. 1 para. 7 in force at 30.7.2013, see reg. 1(b)
8. Particulars of any appointment made by the Agency under section 15 of the 1975 Act.E+W
Commencement Information
I8Sch. 1 para. 8 in force at 30.7.2013, see reg. 1(b)
9. Particulars of any appointment made by the Agency under section 16 of the 1975 Act, including the date on which they were taken.E+W
Commencement Information
I9Sch. 1 para. 9 in force at 30.7.2013, see reg. 1(b)
10. Whether the large raised reservoir is designated as high-risk.E+W
Commencement Information
I10Sch. 1 para. 10 in force at 30.7.2013, see reg. 1(b)