Search Legislation

The Triton Knoll Offshore Wind Farm Order 2013

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

  1. Introductory Text

  2. 1.Citation and commencement

  3. 2.Interpretation

  4. 3.Development consent etc granted by the Order

  5. 4.Maintenance of authorised project

  6. 5.Operation of electricity generating station

  7. 6.Benefit of the Order

  8. 7.Abatement of works abandoned or decayed

  9. 8.Deemed licence under the Marine and Coastal Access Act 2009

  10. 9.Saving for Trinity House

  11. 10.Crown rights

  12. 11.Certification of plans etc

  13. 12.Arbitration

  14. Signature

    1. Expand +/Collapse -

      SCHEDULE 1

      Authorised Project

      1. PART 1 Authorised Development

      2. PART 2 Ancillary Works

      3. Expand +/Collapse -

        PART 3 Requirements

        1. 1.Interpretation

        2. 2.Time limits

        3. 3.Detailed design parameters

        4. 4.Further offshore design requirements

        5. 5.(1) The total number of offshore substations forming part of...

        6. 6.The total length of the cables comprising Work No. 1(c)...

        7. 7.(1) No monopile foundation forming part of the authorised development...

        8. 8.Offshore safety management

        9. 9.Aids to navigation

        10. 10.The undertaker shall ensure that timely and efficient notices to...

        11. 11.The undertaker shall notify Trinity House as soon as reasonably...

        12. 12.The undertaker shall provide reports on the availability of aids...

        13. 13.The undertaker shall notify the UK Hydrographic Office of the...

        14. 14.(1) The undertaker shall colour all structures yellow from at...

        15. 15.Provision against danger to navigation

        16. 16.Air traffic

        17. 17.Lighting

        18. 18.(1) Each wind turbine generator forming part of the authorised...

        19. 19.Onshore traffic management

        20. 20.Aggregates dredging

        21. 21.Pipeline or cable crossings

        22. 22.Offshore decommissioning

        23. 23.Requirement for written approval

    2. Expand +/Collapse -

      SCHEDULE 2

      Deemed licence under the Marine and Coastal Access Act 2009

      1. Expand +/Collapse -

        PART 1 Licensed Marine Activities

        1. 1.Interpretation

        2. 2.Details of licensed marine activities

        3. 3.This licence shall remain in force until the authorised scheme...

      2. Expand +/Collapse -

        PART 2 Conditions

        1. 1.Design parameters for wind turbines

        2. 2.Further offshore design requirements

        3. 3.(1) The total number of offshore substations forming part of...

        4. 4.(1) The total length of the cables comprising Work No....

        5. 5.(1) No steel monopile foundation forming part of the authorised...

        6. 6.Notifications and inspections

        7. 7.Chemicals, drilling and debris

        8. 8.Force majeure

        9. 9.Pre-construction plans and documentation

        10. 10.(1) Each programme, statement, plan, protocol or scheme required to...

        11. 11.Reporting of engaged agents, contractors and vessels

        12. 12.Equipment and operation of vessels engaged in licensed activities

        13. 13.Pre-construction monitoring

        14. 14.Construction monitoring

        15. 15.Post construction surveys

        16. 16.Herring spawning

  15. Explanatory Note