The Electricity (Competitive Tenders for Offshore Transmission Licences) Regulations 2013

2.  The requirements in this paragraph are that the developer has–

(a)entered into a bilateral agreement with the holder of a co-ordination licence in accordance with the arrangements for connection and use of the transmission system;

(b)entered into an agreement for lease of the seabed with the Crown Estate Commissioners;

(c)obtained all necessary consents and property rights for the transmission assets to be constructed and maintained and ensured that any such consents or property rights which are capable of being assignable to the successful bidder are so assignable;

(d)completed construction of, or entered into all necessary contracts for the construction of the transmission assets and ensured that any such contracts are assignable to the successful bidder; and

(e)secured financing to construct the transmission assets.