Decommissioning

40.—(1) There must be submitted to the relevant planning authority within twelve (12) months of the authorised development ceasing to be used for the purposes of electricity generation a site closure and restoration plan for the demolition and removal of the authorised development from the site for approval by the relevant planning authority, in consultation with the Environment Agency. The scheme must include the principles in paragraphs 4.6.9 to 4.6.13 of the environmental statement and also include—

(a)details of all structures and buildings which are to be demolished;

(b)consideration of the effects of leaving below-ground structures permanently in-situ in a dynamic coastal and marine environment together with details of consultations undertaken to consider the need to remove any or all of those structures;

(c)details of the means of removal of the materials resulting from the demolition and measures for the control of dust and noise;

(d)phasing of the demolition and removal works;

(e)details of the restoration works to restore the Order land to a condition agreed with the relevant planning authority;

(f)details of the restoration works and their phasing;

(g)details of the temporary lighting scheme (if any) proposed to be used during decommissioning works;

(h)details of any remediation works required to remove contaminants from the Order land together with details of how such contaminants will be safely disposed of; and

(i)details of how those mitigation measures implemented for the protection of ornithology and ecology during construction would also be implemented during the decommissioning phase.

(2) The demolition and removal of the authorised development (which must include all building structures, plant, equipment, areas of hard standing and access roads) and subsequent restoration of the site must thereafter be carried out fully in accordance with the approved scheme.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources