17.—(1) No authorised development is to commence until a construction environmental management plan has been submitted to and approved in writing by the relevant planning authority.
(2) The construction environmental management plan must be prepared in accordance with the provisions of the approved code of construction practice, and must reflect the mitigation measures included in the environmental statement.
(3) The construction environmental management plan may incorporate the plans, schemes and details required to be approved in writing by other requirements set out in this Schedule.
(4) The authorised development must be carried out in accordance with the provisions of the construction environmental management plan.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: