There are currently no known outstanding effects for the The Waste Electrical and Electronic Equipment Regulations 2013, PART 14. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 14U.K.OFFENCES AND PENALTIES

OffencesU.K.

90.—(1) A producer or authorised representative will be guilty of an offence if he—

(a)contravenes or fails to comply with any requirements of regulation 11, 12, 13, 14, 15, 16, 17, 18, 19 or 20;

(b)furnishes information under regulation 16 or 18 and either—

(i)knows the information provided to be false or misleading in a material particular, or

(ii)furnishes such information recklessly and it is false or misleading in a material particular; or

(c)furnishes a declaration of compliance under regulation 19 and either—

(i)knows the information provided in, or in connection with, the declaration to be false or misleading in a material particular, or

(ii)furnishes such information recklessly and it is false or misleading in a material particular.

(2) A producer or authorised representative will be guilty of an offence if he contravenes or fails to comply with any requirements of regulation 21, 22, 23 or 24.

(3) An operator of a scheme will be guilty of an offence if he—

(a)contravenes or fails to comply with any requirements of regulation 26, 27, 28, 29, 31, 32, 35, 36, 37, 38, 39, 40, 41 or 57;

(b)furnishes a report under either regulation 35 or 37; and 36 or 38 and either—

(i)knows the information provided in, or in connection with, the report to be false or misleading in a material particular, or

(ii)furnishes such information recklessly and it is false or misleading in a material particular; or

(c)furnishes a declaration of compliance under regulation 39 and either—

(i)knows the information provided in, or in connection with, the declaration to be false or misleading in a material particular, or

(ii)furnishes such information recklessly and it is false or misleading in a material particular.

(4) An operator of a scheme will be guilty of an offence if he contravenes or fails to comply with any requirements of regulation 30.

(5) A distributor will be guilty of an offence if he contravenes or fails to comply with any requirements of regulation 42 or 69.

(6) A distributor will be guilty of an offence if he contravenes or fails to comply with any requirements of regulation 44 or 45.

(7) An operator of an AATF or an approved exporter is guilty of an offence if he—

(a)contravenes or fails to comply with any requirements of regulation 54, 61, 63, 66 or 67; or

(b)furnishes a report under regulation 66 and either—

(i)knows the information provided in, or in connection with, the report to be false or misleading in a material particular, or

(ii)furnishes such information recklessly and it is false or misleading in a material particular.

(8) A person will be guilty of an offence if he—

(a)contravenes or fails to comply with any requirements of regulation 47, 51 or 60;

(b)without reasonable cause, fails to comply with an enforcement notice served under regulation 88;

(c)without reasonable cause, fails to comply with a requirement imposed under regulation 89;

(d)intentionally obstructs any person acting in the execution of these Regulations;

(e)without reasonable cause, fails to give to any person acting in the execution of these Regulations any assistance or information which that person may reasonably require of him for the performance of his functions under these Regulations;

(f)without reasonable cause, fails to produce information when required to do so to any person acting in the execution of these Regulations;

(g)furnishes to any person acting in the execution of these Regulations any information which he—

(i)knows the information to be false or misleading in a material particular, or

(ii)furnishes such information recklessly and it is false or misleading in a material particular.

(9) A person will be guilty of an offence if he contravenes or fails to comply with any requirements of regulation 48.

(10) If an offence under these Regulations committed by a body corporate is shown—

(a)to have been committed with the consent or connivance of an officer, or

(b)to be attributable to any neglect on the part of the officer,

(c)the officer as well as the body corporate is guilty of the offence and liable to be proceeded against and punished accordingly.

(11) If the affairs of a body corporate are managed by its members, paragraph (10) applies in relation to the acts and defaults of a member in connection with the functions of management of that member as if the member were a director of the body.

(12) If an offence under these Regulations committed by a partnership is shown—

(a)to have been committed with the consent or connivance of a partner; or

(b)to be attributable to neglect on the part of a partner,

the partner as well as the partnership is guilty of the offence and liable to be proceeded against and punished accordingly.

(13) If an offence under these Regulations committed by an unincorporated body, other than a partnership, is shown—

(a)to have been committed with the consent or connivance of an officer of the body or a

(b)member of its governing body, or

(c)to be attributable to any neglect on the part of such an officer or member,

(d)that officer or member as well as the body is guilty of the offence and liable to be proceeded against and punished accordingly.

(14) In this regulation—

(a)“officer”, in relation to a body corporate, means a director, member of the committee of management, chief executive, manager, secretary or other similar officer of the body, or a person purporting to act in any such capacity; and

(b)“partner” includes a person purporting to act as a partner.

(15) Where an offence under these Regulations is committed by a Scottish partnership and is proved to have been committed with the consent or connivance of, or have been attributable to neglect on the part of, any partner or a person who was purporting to act as such, that person as well as the partnership will be guilty of that offence and will be liable to be proceeded against and punished accordingly.

Commencement Information

I1Reg. 90 in force at 1.1.2014, see reg. 1(2)

PenaltiesU.K.

91.—(1) A person who is guilty of an offence under regulation 90(1), (3), (5), (7), (8), (12), (13) or (15) will be liable—

(a)on summary conviction, to a fine not exceeding the statutory maximum;

(b)on conviction on indictment, to a fine.

(2) A person who is guilty of an offence under regulation 82(6), 89(10) or 90(2), (4), (6) or (9) will be liable on summary conviction to a fine not exceeding level 5 on the standard scale.

Commencement Information

I2Reg. 91 in force at 1.1.2014, see reg. 1(2)

Commencement of proceedingsU.K.

92.—(1) In England and Wales a magistrates’ court may try an information, and in Northern Ireland a magistrates’ court may try a complaint, in relation to an offence under these Regulations if the information is laid or if the complaint is made within twelve months from the time when the offence is committed.

(2) In Scotland proceedings in relation to any offence which under these Regulations is triable only by way of summary proceedings, may be begun at any time within twelve months from the time when the offence is committed.

Commencement Information

I3Reg. 92 in force at 1.1.2014, see reg. 1(2)

ReviewU.K.

93.—(1) The Secretary of State must from time to time—

(a)carry out a review of these Regulations;

(b)set out the conclusions of the review in a report; and

(c)publish the report.

(2) In carrying out the review the Secretary of State must, so far as is reasonable, have regard to how the Directive is implemented in other Member States.

(3) The report must in particular—

(a)set out the objectives intended to be achieved by the regulatory system established by these Regulations;

(b)assess the extent to which those objectives are achieved; and

(c)assess whether those objectives remain appropriate and, if so, the extent to which they could be achieved with a system that imposes less regulation.

(4) The first report under this regulation must be published before the end of the period of five years beginning with the day on which these Regulations come into force.

(5) Reports under this regulation are afterwards to be published at intervals not exceeding five years.

Commencement Information

I4Reg. 93 in force at 1.1.2014, see reg. 1(2)

Consequential amendmentsE+W+S

94.  In section 56 (interpretation of Part 1) of the Environment Act 1995(1), in subsection (1) in the definition of “environmental licence” in the application of Part 1 of that Act in relation to the Environment Agency and the National Resources Body for Wales—

(a)for paragraph (l) substitute “(l) approval of a scheme under regulation 55 of the Waste Electrical and Electronic Regulations 2013 (“the WEEE Regulations”).”

(b)for paragraph (m) substitute “(m) compliance with the condition in regulation 57(f)(i) of the WEEE Regulations in relation to a scheme mentioned in paragraph (l).”

(c)for paragraph (n) substitute “(n) approval of an authorised treatment facility or exporter under regulation 61 of the WEEE Regulations.”; and

(d)for paragraph (o) substitute “(o) extension of approval of an exporter under regulation 62 of the WEEE Regulations.”.

(2) In the definition of “environmental licence” in the application of Part 1 of that Act in relation to the Scottish Environmental Protection Agency—

(a)for paragraph (l) substitute “(l) approval of a scheme under regulation 55 of the Waste Electrical and Electronic Regulations 2013 (“the WEEE Regulations”).”

(b)for paragraph (m) substitute “(m) compliance with the condition in regulation 57(f)(i) of the WEEE Regulations in relation to a scheme mentioned in paragraph (l).”

(c)for paragraph (n) substitute “(n) approval of an authorised treatment facility or exporter under regulation 61 of the WEEE Regulations.”; and

(d)for paragraph (o) substitute “(o) extension of approval of an exporter under regulation 62 of the WEEE Regulations.”.

Commencement Information

I5Reg. 94 in force at 1.1.2014, see reg. 1(2)

Transitional provisionsU.K.

95.—(1) Any application made or approval granted by an appropriate authority under regulations 10, 20 or 47 of the Waste Electrical and Electronic Equipment Regulations 2006 will continue to have effect as though it had been granted in accordance with these Regulations.

(2) Any environmental licence granted by an appropriate authority under regulation 4 of the Waste Electrical and Electronic Equipment Regulations 2006 will continue to have effect as though it had been granted under these Regulations.

Commencement Information

I6Reg. 95 in force at 1.1.2014, see reg. 1(2)

Revocations and SavingsU.K.

96.—(1) The following instruments are revoked by these Regulations—

(a)The Waste Electrical and Electronic Equipment (Amendment) Regulations (SI 2007/3454);

(b)The Waste Electrical and Electronic Equipment (Amendment) Regulations 2009 (SI 2009/2957);

(c)The Waste Electrical and Electronic Equipment (Amendment) (No. 2) Regulations 2009 (SI 2009/3216);

(d)The Waste Electrical and Electronic Equipment (Amendment) Regulations 2010 (SI 2010/1155);

(2) Subject to paragraphs (3) and (4) the Waste Electrical and Electronic Equipment Regulations 2006 (SI 2006/3289) are revoked.

(3) Regulation 4 of the Waste Electrical and Electronic Equipment Regulations 2006 (SI 2006/3289) will continue to have effect.

(4) Regulation 66 and Schedule 11 of the Waste Electrical and Electronic Equipment Regulations 2006 will continue to have effect in respect of appeals commenced on or before 31st December 2013.

(5) The provisions referred to in paragraphs (3) and (4) will continue to apply as they did immediately before their revocation for all of the purposes in relation to the collection, treatment and recycling of WEEE.

Commencement Information

I7Reg. 96 in force at 1.1.2014, see reg. 1(2)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources