SCHEDULES

SCHEDULE 11Approval of authorised treatment facilities and exporters

PART 2Conditions of approval of authorised treatment facilities

24

From 1st January 2019 WEEE treated at the relevant AATF will meet the following targets—

a

for WEEE that falls within categories 1 and 4 of Schedule 3—

i

at least 85% recovery by the average weight in tonnes of the equipment,

ii

at least 80% reuse and recycling of components, materials and substances by the average weight in tonnes of the equipment;

b

for WEEE that falls within category 2 of Schedule 3—

i

at least 80% recovery by the average weight in tonnes of the equipment,

ii

at least 70% reuse and recycling of components, materials and substances by the average weight in tonnes of the equipment;

c

for WEEE that falls within categories 5 or 6 of Schedule 3—

i

at least 75% recovery by the average weight in tonnes of the equipment,

ii

excluding gas discharge lamps and LED light sources, at least 55% reuse and recycling of components, materials and substances by the average weight in tonnes of the equipment;

d

for WEEE falling within category 3 at least 80% reuse and recycling of components, materials and substances by the average weight in tonnes of the lamps.