3.—(1) No authorised development shall commence until the location and detailed specifications for Work Nos. 2a and 2b above mean low water level have been submitted to and approved in writing by the local planning authority.
(2) The detailed specifications for Work Nos. 2a and 2b above mean low water level shall accord with the principles of the project design statement and shall only take place within the limits of deviation.
(3) Work Nos. 2a and 2b must be carried out in accordance with the details approved under sub-paragraph (1).
(4) Subject to sub-paragraphs (1) and (2), the authorised development must be carried out in accordance with—
(a)the Order limits plan; and
(b)the works plan.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: