9. For the purpose of requirements BRIC1 to BRIC18, the “site” refers to the land within the Order limits shown on sheet no. 13 and “development” refers to Work Nos. 5A and 5B. Requirements BRIC1 to BRIC18 relate only to development carried out on the site as so defined.
(1) Reference No. | (2) Requirements | |
---|---|---|
BRIC1 | Car parking | |
The number of car parking spaces to be provided and available for Work No. 5A for the duration of the HPC construction works shall not exceed 66, unless otherwise approved by Sedgemoor District Council. | ||
BRIC2 | Vegetation clearance | |
(1) No vegetation clearance within the period from March to August inclusive shall be carried out unless and until a scheme designed to avoid or reduce impacts on breeding birds has been submitted to and approved by Sedgemoor District Council. | ||
(2) Any vegetation clearance undertaken during the period March to August inclusive shall be carried out in accordance with the approved scheme. | ||
(3) All vegetation clearance works shall be undertaken under the supervision of an ecological clerk of works. | ||
BRIC3 | Construction compound | |
(1) Buildings, structures, plant, equipment, uses, construction hoardings and means of enclosure required in connection with construction of the development shall be built and used in accordance with section 6 of the Construction Method Statement and as set out in Figure 3.1 (Environmental Statement, Volume 4) Construction Work Area and Access Plan, unless otherwise approved by Sedgemoor District Council. | ||
(2) Following completion of construction works on site, all temporary structures, plant and equipment required for construction of the development shall be removed. | ||
BRIC4 | Temporary Canteen Facility | |
(1) Construction of the Temporary Canteen Facility (comprised in Work No. 5A(e)) shall not commence until details of its siting, scale and external appearance have been submitted to and approved by Sedgemoor District Council. | ||
(2) The details referred to in paragraph (1) shall be in accordance with sections 6 (Design Principles) and 9 (Parameters for Implementation) of the BRI C Accommodation Campus Design and Access Statement. | ||
(3) The Temporary Canteen Facility shall be implemented in accordance with the approved details. | ||
BRIC5 | Landscape works | |
(1) No development shall commence until a landscape scheme has been submitted to and approved by Sedgemoor District Council. The landscape scheme shall be developed in general accordance with the landscape strategy drawing 500103 (Rev 01): Proposed Hard and Soft Landscape Works During Operation and 500100 (Rev 01): Tree and Hedgerow Retention and Removal Plan, and section 6 (Design Principles) and section 7 (Development Proposals) of the Bridgwater C Design and Access Statement. The landscape scheme shall include details of all proposed hard and soft landscape works, including— | ||
(a) | soft landscape details; | |
(b) | proposed finished ground levels; | |
(c) | hard surfacing materials; | |
(d) | vehicular and pedestrian access, parking and circulation areas; | |
(e) | street furniture, security cabins, bus shelters, refuse or other storage units; | |
(f) | details of existing trees to be retained, with measures for their protection during construction of the development; | |
(g) | plant establishment, maintenance and management arrangements; and | |
(h) | an implementation timetable for all landscaping works. | |
(2) All landscape works must be carried out in accordance with the landscape scheme approved under this requirement and in accordance with the relevant recommendations of appropriate British Standards. | ||
BRIC6 | Highways | |
(1) The site access shall be carried out in accordance with the drawings 830208(Rev 01): Site Entrance Layout and 001001 (Rev 01): Proposed Highways General Arrangement Plan, unless otherwise approved by Sedgemoor District Council. | ||
(2) No works shall be carried out otherwise than in accordance with the approved plans. | ||
(3) Work No. 5A shall not be brought into use until Work No. 5B and the site access are available for use. | ||
BRIC7 | Fencing | |
(1) Except for fencing erected pursuant to requirement BRIC3, no security fences, walls or other means of enclosure shall be erected until details of their layout, scale and appearance have been submitted to and approved by Sedgemoor District Council. | ||
(2) Work No. 5A must remain securely fenced at all times during construction and operation of Work No. 5A. | ||
BRIC8 | Lighting | |
(1) Installation of external lighting shall not commence until details of external lighting, including a scheme for the management and mitigation of artificial light emissions, has been submitted to and approved by Sedgemoor District Council. The lighting scheme shall be in accordance with section 7 (Development Proposals) of the Bridgwater C Design and Access Statement. | ||
(2) The approved scheme for the management and mitigation of artificial light emissions must be implemented and maintained during the construction and operation of the development. | ||
BRIC9 | Signage | |
(1) Except for signage which the undertaker is permitted to erect by virtue of the Town and Country Planning (Control of Advertisement) Regulations 2007 or any signage set out in the approved plans, no signage shall be erected on the site until details of the location, size, colour, projection and method of any illumination have been submitted to and approved by Sedgemoor District Council. Signage details shall be in accordance with section 6 (Design Principles) of the Bridgwater C Design and Access Statement. | ||
(2) Signage referred to in paragraph (1) shall be implemented in accordance with the approved details. | ||
BRIC10 | Flood Risk Assessment | |
The development shall be carried out in accordance with the recommendations set out in sections 5 and 6 of the Bridgwater C Flood Risk Assessment, unless otherwise approved by Sedgemoor District Council. | ||
BRIC11 | Finished floor levels | |
(1) Construction of the Bridgwater C accommodation campus buildings (Work No. 5A(e) shall not commence until details of all proposed finished floor levels have been submitted to and approved by Sedgemoor District Council. Accommodation floor levels shall be set no lower than 7.5m above ordnance datum (N), or no lower than +150mm above existing ground levels, as recommended by Section 7.1.6 of the Bridgwater C Flood Risk Assessment. | ||
(2) The development shall be carried out in accordance with the details approved under paragraph (1). | ||
BRIC12 | Surface and foul water | |
(1) No works shall commence until details of the surface and foul water drainage system (including means of pollution control and details of the future responsibility and maintenance arrangements) have, after consultation with the Environment Agency, the sewerage authority and drainage authority (Parrett Internal Drainage Board), been submitted to and approved by Sedgemoor District Council. | ||
(2) The surface and foul water drainage system shall be constructed in accordance with the approved details. | ||
BRIC13 | Infiltration of surface water drainage | |
(1) No infiltration of surface water drainage into the ground shall be permitted unless and until details demonstrating that there is no unacceptable risk to controlled waters have, following consultation with the Environment Agency, been submitted to and approved by Sedgemoor District Council. | ||
(2) The development shall be carried out in accordance with the approved details. | ||
BRIC14 | Migration paths for contaminants | |
(1) The development shall not commence until a scheme to treat and remove suspended solids, hydrocarbons and concrete leachate, and any other potential contaminant, from surface water run-off during construction works has, after consultation with the sewerage and drainage authority, been submitted to and approved by Sedgemoor District Council. | ||
(2) The development shall be carried out in accordance with the details approved under paragraph (1). | ||
BRIC15 | Post-operation | |
All proposed buildings on the site of Work No. 5A shall be demolished, and all materials resulting from their demolition shall be removed from the site, within 12 months of the completion of the HPC construction works. | ||
BRIC16 | Contamination | |
(1) No development shall commence until a remediation strategy that takes into account the findings of the Factual Report on Ground Investigation at Associated Developments Bridgwater C Campus, Phases I, II and III (Volume 4 of the Environmental Statement, Appendix 12B), has been submitted to and approved by Sedgemoor District Council. | ||
(2) Following completion of the remediation strategy referred to in paragraph (1), a verification plan shall be submitted to Sedgemoor District Council detailing data to be collected in order to demonstrate that the remediation strategy set out in paragraph (1) has been fully implemented and which identifies any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action. | ||
(3) The remediation strategy referred to in paragraph (1) shall be implemented as approved. | ||
BRIC17 | Piling | |
(1) No piling or any other foundation designs using penetrative methods shall be used, or underground services installed, unless and until details demonstrating that there is no unacceptable risk to controlled waters have, in consultation with the Environment Agency, been submitted to and approved by Sedgemoor District Council. | ||
(2) The development shall be carried out in accordance with the approved details. | ||
BRIC18 | Sports Pitches | |
The external sports facilities shall not be used or associated lighting operated between the hours of 22:00 and 08:00. |