15.—(1) Work No. 7A and 7B shall not commence until a written scheme for compensatory flood storage has been submitted to and has, after consultation with the Environment Agency, been approved by the Enfield London Borough Council.
(2) The compensatory flood storage shall be constructed in accordance with the approved scheme.
(3) The written scheme of flood compensation shall include—
(a)a schedule of staging and timing relating to the construction of Work No. 7A, 7B and the compensatory flood storage;
(b)flood storage up to and including the modelled 1 to 100 chance in any year including a 20% allowance for climate change flood level; and
(c)no increase in flood risk off site.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: