SCHEDULE 9Protective provisions

PART 3Protection of Network Rail Infrastructure Limited

10

The undertakers must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—

a

in constructing any part of a specified work on behalf of the undertakers as provided by paragraph 5(3) or in constructing any protective works under the provisions of paragraph 5(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;

b

in respect of the approval by the engineer of plans submitted by the undertakers and the supervision by the engineer of the construction of a specified work;

c

in respect of the employment or procurement of the services of any inspectors, signalmen, watchmen and other persons whom it shall be reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;

d

in respect of any special traffic working resulting from any speed restrictions which may in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or from the substitution or diversion of services which may be reasonably necessary for the same reason; and

e

in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work.