Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1. These Regulations may be cited as the Energy Savings Opportunity Scheme Regulations 2014 and come into force on 17th July 2014.
2.—(1) In these Regulations—
“approval body” has the meaning given in regulation 12(4)(b);
“approved list” has the meaning given in regulation 12(5);
“approved register” has the meaning given in regulation 12(4)(a);
[F1“areas of significant energy consumption” has the meaning given in regulation 25(2);]
“certified energy management system” has the meaning given in regulation 33(1);
“Chief Inspector” has the meaning given in regulation 6(1)(b);
“compliance body” has the meaning given in regulation 6(1);
“compliance date” has the meaning given in regulation 4(4);
“compliance notice” has the meaning given in regulation 35(1);
“the Directive” means Directive 2012/27/EU of the European Parliament and of the Council on energy efficiency M1;
“display energy certificate” has the meaning given in regulation 34(4)(a);
“employee” has the meaning given in—
“energy” has the meaning given in Article 2(1) of the Directive;
“energy audit” means an audit carried out, as part of an ESOS assessment, in accordance with Chapter 3 of Part 4;
“energy consumption” has the meaning given in regulation 23(1);
“energy efficiency” has the meaning given in Article 2(4) of the Directive;
[F1“energy intensity ratio” has the meaning given in regulation 25C(2);]
“energy measurement unit” means a unit by which the supply or consumption of energy is commonly measured;
[F1“energy saving category” means one of the following methods by which a participant can improve its energy efficiency—
an energy management practice,
a behaviour change intervention,
training,
a control,
capital investment, or
a method not falling within paragraph (a) to (e);]
[F1“energy saving measure” has the meaning given in regulation 27A(7)(d);]
[F1“energy saving opportunity” has the meaning given in regulation 27(1)(c);]
“enforcement notice” has the meaning given in regulation 38(1);
[F1“ESOS action plan” has the meaning given in regulation 34A(3);]
“ESOS assessment” means an assessment carried out in accordance with Part 4;
[F1“ESOS progress update” has the meaning given in regulation 34B(2);]
[F1“ESOS report” has the meaning given in regulation 27A(4);]
“evidence pack” has the meaning given in regulation 28(1);
“group undertaking” has the meaning given in section 1161(5) of the Companies Act 2006 M4;
“highest parent” has the meaning given in regulation 17(3);
“highest parent group” has the meaning given in regulation 17(2);
“initial compliance period” has the meaning given in regulation 4(1);
[F1“kWh” means kilowatt hours;]
“lead assessor” has the meaning given in regulation 11;
“legislative provision” means an enactment, including—
an enactment comprised in, or in an instrument made under, an Act of the Scottish Parliament, and
Northern Ireland legislation;
“Notification System” has the meaning given in regulation 8(1);
“offshore activity” means activity which includes—
the exploitation of mineral resources in or under the shore or bed of waters in the offshore area,
the conversion of a place under the shore or bed of such waters for the purpose of storing gas,
the storage of gas in, under or over such waters or the recovery of gas so stored,
the unloading of gas at a place in, under or over such waters, and
the provision of accommodation for persons who work on or from an offshore installation which is maintained for the production of petroleum or the storage or unloading of gas
where storing gas includes storing gas with a view to its permanent disposal, and “gas” means gas within the meaning of section 2(4) of the Energy Act 2008 M5 or carbon dioxide;
“offshore area” means—
the sea adjacent to England, Scotland, Wales and Northern Ireland from the low water mark to the landward baseline of the United Kingdom territorial sea,
the United Kingdom territorial sea adjacent to England, Scotland, Wales and Northern Ireland,
the sea in any designated area within the meaning of section 1(7) of the Continental Shelf Act 1964 M6, and
the sea in any area for the time being designated under section 41(3) of the Marine and Coastal Access Act 2009(d)
and includes the places above those areas, and the bed and subsoil of the sea within those areas;
“offshore installation” means an installation or structure used for carrying on an offshore activity, which is situated in the waters of, or on the seabed in, the offshore area, but excluding a ship or a floating structure which is not being maintained on station during the course of an offshore activity;
“offshore undertaking” means an undertaking whose activities consist wholly or mainly of offshore activities;
[F1“organisational purpose” means one of the following purposes for which energy is consumed by assets held, or activities are carried on, by a participant—
for transport,
for an industrial process,
for buildings, or
for any other purpose not falling within paragraph (a) to (c);]
“parent undertaking” has the meaning given in section 1162 of the Companies Act 2006;
“participant” has the meaning given in regulation 17(1);
“the PAS” has the meaning given in regulation 12(1);
“penalty notice” has the meaning given in regulation 39(1);
“premises” means any land, vehicle or vessel, or any plant which is designed to move or be moved;
“publication penalty” has the meaning given in regulation 41(1);
“qualification date” has the meaning given in regulation 4(3);
“qualifying Green Deal assessment” has the meaning given in regulation 34(4)(b);
[F1“reference period” has the meaning given in regulation 22(5);]
“relevant undertaking” has the meaning given in regulation 15(1);
“responsible officer” has the meaning given in regulation 30(2);
“responsible undertaking” has the meaning given in regulation 18;
“the Scheme” means the Energy Savings Opportunity Scheme established by these Regulations;
“scheme administrator” has the meaning given in regulation 5;
[F1“significant energy consumption” has the meaning given in regulation 25(4);]
[F1“standard industrial classification” means the Office for National Statistics’ “UK Standard Industrial Classification of Economic Activities 2007 (SIC 2007);]
“subsequent compliance period” has the meaning given in regulation 4(2);
“subsidiary undertaking” has the meaning given in section 1162 of the Companies Act 2006;
“undertaking” has the meaning given in section 1161(1) of the Companies Act 2006;
“working day” means any day other than—
a Saturday or a Sunday,
Christmas Day or Good Friday, or
a bank holiday within the meaning of section 1 of the Banking and Financial Dealings Act 1971 M7.
(2) Save as otherwise appears, any reference in these Regulations to a numbered Part, Chapter or regulation is a reference to that numbered Part, Chapter or regulation in these Regulations.
Textual Amendments
F1Words in reg. 2(1) inserted (29.11.2023) by The Energy Savings Opportunity Scheme (Amendment) Regulations 2023 (S.I. 2023/1182), regs. 1(2), 3
Marginal Citations
M1OJ No L 315, 14.11.2012, p1, to which there is an amendment not relevant to these Regulations. Article 8(4) to (6) is transposed by these Regulations.
M31996 No. 1919 (N.I. 16).
M61964 c. 29, amended by paragraph 1 of Schedule 3 to the Oil and Gas (Enterprise) Act 1982 (c. 23), and by section 103 of the Energy Act 2011 (c. 16).
(d)2009 c. 23.
3.—(1) At intervals of no more than 5 years, the Secretary of State must—
(a)carry out a review of the operation and effect of these Regulations,
(b)publish the conclusions of the review in a report.
(2) In carrying out a review the Secretary of State must, so far as is reasonable, have regard to how Article 8(4) to (6) of the Directive is transposed in other Member States.
(3) Any report must in particular—
(a)set out the objectives intended to be achieved by these Regulations,
(b)assess the extent to which those objectives are achieved,
(c)assess whether those objectives remain appropriate, and
(d)where the objectives remain appropriate, assess the extent to which they could be more effectively achieved.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: