44.—(1) Each liable electricity supplier must pay to the Settlement Body a settlement costs levy calculated in accordance with this regulation in respect of the first levy period.
(2) Subject to paragraph (3), the prescribed amount is £1,374,000.
(3) If the appointment date is on or after 1st September 2014, the prescribed amount is to be reduced by £100,000 for each full calendar month between 31st July 2014 and the appointment date.
(4) The Settlement Body must, as soon as reasonably practicable after the end of the first levy period—
(a)calculate the amount of the settlement costs levy to be paid by each liable electricity supplier; and
(b)issue an invoice to each liable electricity supplier for the amount to be paid by that supplier.
(5) The calculation under paragraph (4)(a) must be made in accordance with paragraph 9 of Schedule 1.
(6) In this regulation—
“the appointment date” means the date on which the Secretary of State first appoints a Settlement Body under regulation 80;
“the first levy period” means the period commencing on the appointment date and ending on 31st March 2015; and
“liable electricity supplier” means an electricity supplier which supplied electricity to customers in Great Britain in the first levy period;
“the prescribed amount” means the total amount of the settlement costs levy to be invoiced to liable electricity suppliers in respect of the first levy period;
“settlement costs” means costs incurred by the Settlement Body in connection with the performance of its functions under electricity capacity regulations and capacity market rules;
“settlement costs levy” means the levy imposed by this regulation on liable electricity suppliers in respect of settlement costs.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: