Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThe Whole
Chapter
PrintThis
Section
only
Changes over time for: Section 27


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 01/08/2014.
Changes to legislation:
There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Electricity Capacity Regulations 2014. Any changes that have already been made by the team appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Power to annul capacity auctionE+W+S
This section has no associated Explanatory Memorandum
27.—(1) The Secretary of State may, within 7 working days after a capacity auction is completed, annul the capacity auction if it appears to the Secretary of State that there are reasonable grounds to suspect that—
(a)there was an irregularity in relation to the capacity auction; and
(b)the irregularity affected—
(i)the auction clearing price; or
(ii)the CMUs which were successful in the capacity auction.
(2) For the purposes of paragraph (1) there is an irregularity if, but only if, the capacity auction was not conducted in accordance with regulation 24(3).
(3) If the Secretary of State decides to annul a capacity auction, the Secretary of State must—
(a)immediately publish that decision; and
(b)not later than 4 weeks after making that decision, publish the reasons for it.