Search Legislation

The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Development consent etc. granted by the Order

3.  Subject to the provisions of this Order and to Schedule 3 (requirements) and Schedule 16 (protective provisions) to this Order the undertaker is granted—

(a)development consent for the authorised development; and

(b)consent for the ancillary works;

to be carried out within the Order limits and in accordance with the approved plans.