PART 2WORKS PROVISIONS

Principal powers

Defence to proceedings in respect of statutory nuisance7

1

Where proceedings are brought under section 82(1) of the Environmental Protection Act 199019 (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraph (g) of Section 79(1) of that Act (noise emitted from premises so as to be prejudicial to health or a nuisance) no order shall be made, and no fine may be imposed, under section 82(2) of that Act if the defendant shows that the nuisance—

a

relates to premises used by the undertaker for the purposes of or in connection with the construction of the authorised project and associated activities up to completion of construction and that the nuisance is attributable to the carrying out of the authorised project in accordance with a notice served under section 60 (control of noise on construction sites), or a consent given under section 61 (prior consent for work on construction sites) or 65 (noise exceeding registered level), of the Control of Pollution Act 1974; or

b

is a consequence of complying with a requirement of this Order and that it cannot reasonably be avoided; or

c

is a consequence of the construction of the authorised project before completion of construction and that it cannot reasonably be avoided.

2

Section 61(9) of the Control of Pollution Act 1974 (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), shall not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project.

3

The defence in this article shall not have effect after completion of construction.