Search Legislation

The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Abbey Mills Pumping Station

25.  The table below sets out the specific requirements for the Abbey Mills Pumping Station site—

TitleRefText
CoCP Part BABMPS1Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders.
Detailed design approval for permanent above-ground structuresABMPS2

(1) Construction of any permanent above-ground structure shall not commence until details of the design (including size, external appearances and materials), which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE.

Contaminated landABMPS3

Site-specific remediation strategy

(1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency—

a. a preliminary risk assessment and site investigation scheme which identifies—

all previous uses

potential contaminants associated with those uses

a conceptual model of the site indicating sources, pathways and receptors

a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site

a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site.

b. a remediation strategy which includes—

a detailed quantitative risk assessment

an options appraisal giving full details of the remediation measures required and how they shall be carried out

a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action

a programme for the submission of elements detailed in (3) and (4) below.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency.

Verification report

(3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan.

(4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency.

Unexpected contamination

(5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.

ArchaeologyABMPS4

(1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE.

(2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body.

Construction traffic management planABMPS5

(1) Work No. 26a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL.

Travel planABMPS6

(1) Work No. 26a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL.

(2) The approved travel plan(s) shall be implemented from commencement of Work No. 26a and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL.

Surface water drainageABMPS7

(1) Construction of the permanent above-ground structures or landscaping shall not commence until details of the surface water drainage system for this site (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development.

Heritage interpretationABMPS8

(1) Prior to completion of the works (save for commissioning) any relevant details applicable to this site from the project wide heritage strategy required by PW11 shall be submitted to and approved by the relevant planning authority.

(2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources