CEMP
15.—(1) No part of the authorised development shall be carried out until a CEMP, substantially in accordance with the outline Construction Environmental Management Plan certified by the Secretary of State for the purposes of this Order, has been submitted to and approved by the relevant planning authority.
(2) All construction work shall be carried out in accordance with the approved CEMP unless otherwise approved by the relevant planning authority.