Search Legislation

The North Killingholme (Generating Station) Order 2014

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

CEMP

15.—(1) No part of the authorised development shall be carried out until a CEMP, substantially in accordance with the outline Construction Environmental Management Plan certified by the Secretary of State for the purposes of this Order, has been submitted to and approved by the relevant planning authority.

(2) All construction work shall be carried out in accordance with the approved CEMP unless otherwise approved by the relevant planning authority.

Back to top

Options/Help