36. Until the permanent cessation of commercial operation of the authorised development, the undertaker shall not, without the written consent of the Secretary of State—
(a)dispose of any interest in land which includes the area to be occupied by Work Nos. 2a, 2b, and 2c except by way of a lease having a term of less than 2 years or which is otherwise determinable within 2 years by the undertaker for the purpose of installing the capture equipment; or
(b)do any other thing, or allow any other thing to be done or to occur, which may reasonably be expected to diminish the ability, within the 2 years following such act or occurrence or thereafter, to install and operate the capture equipment on the designated site.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: