Search Legislation

The North Killingholme (Generating Station) Order 2014

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Control of construction noise at North Killingholme Haven Pits

51.—(1) Construction of Work Nos. 6a and 6b adjacent to the North Killingholme Haven Pits, as shown on drawing 64042B-DCO-48, shall not take place except in accordance with a scheme that has been submitted to and approved by the relevant planning authority in consultation with Natural England in advance of such works.

(2) The approved scheme shall address the period outside the months January to March (January to March inclusive being the only months in which piling may occur) and shall have the objective that the rating level of construction noise from the construction of Work Nos. 6a and 6b adjacent to the North Killingholme Haven Pits shall not exceed both the LAeq rating level and the mean LAmax rating level as listed in the following table in any 12 hour period except in case of emergency or unless otherwise as approved by the relevant planning authority, in consultation with Natural England.

LocationRating Level dB,LAeq,12 hourRating Level dB,LAmax (mean)

NSR A, North of Haven Road

(see Drawing Reference 64042B-Natural England-01)

5675

(3) Compliance with the above limits shall be deemed to be achieved through compliance with a programme of attended noise monitoring and periodic site noise audits and equipment condition reviews pursuant to the approved scheme.

(4) The monitoring of noise pursuant to this requirement shall be compliant with the requirements of ISO 1996 Part 2 (2007).

(5) The mean LAmax will be calculated as the logarithmic average of LAmax values recorded at NSR A using a Class A integrating sound level meter, with a 15-minute sampling period, operating continuously throughout the entire construction day. In processing the recorded data to calculate the mean LAmax, the dataset over the course of the construction day could show “sampling periods of no construction activity”. These “sampling periods of no construction activity” will not be included in the mean LA max calculation.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources