SCHEDULE 1Authorised project
PART 3Requirements
NoiseI135
1
No authorised development may commence until an assessment demonstrating that noise from the electrical substation on the site would not exceed a level of 30 dB LAeq at the nearest residential property has been submitted to and approved in writing by the relevant planning authority.
2
The substation is to be constructed in accordance with the approved assessment.